If a builder abandons a real estate project after collecting money from homebuyers, the buyers are not necessarily without legal remedies. Depending on the facts, they may be able to seek refund, interest, compensation, completion of the project, or other appropriate relief.
What can homebuyers do?
1. Check the project's RERA status
Buyers should verify the project's RERA registration, approved details, construction status and any orders or proceedings already recorded by the relevant state RERA authority.
2. Collect all important documents
Buyers should preserve the Agreement for Sale, allotment letter, payment receipts, bank statements, demand letters, correspondence with the builder, possession commitments and evidence showing that construction has stopped.
3. Send a written notice to the builder
The buyers can formally ask the builder to explain the project's status and provide a clear timeline for completion or refund, depending on the circumstances.
4. Approach RERA
If the builder has failed to fulfill its obligations, affected buyers can consider filing a complaint before the appropriate State RERA authority. Depending on the circumstances, buyers may seek remedies such as refund with applicable interest, compensation, possession or directions concerning completion of the project.
5. Consider consumer remedies where appropriate
A homebuyer may also have remedies under consumer-protection law in appropriate circumstances. The correct forum and relief can depend on the facts of the case and the nature of the dispute.
Can buyers get a refund with interest?
Potentially, yes. If the buyer is legally entitled to withdraw because of the builder's failure to complete the project or other serious default, the buyer may seek a refund of the amount paid along with applicable interest and compensation, subject to the applicable law and the decision of the relevant authority.
If several buyers are affected, they may also consider coordinating their legal action and maintaining consistent documentation.
Because the consequences of an abandoned project can be complicated, buyers should review the project documents and current RERA proceedings before deciding whether to pursue refund or completion of the project.